Supply and Installation of Solar panels in Orakzai, Khyber and Bajaur Districts;

This specific tender is managed via the new supplier portal system of UNDP Quantum. If you are interested in submitting a bid for this tender, you must subscribe following the instructions in the user guide. If you have not registered a profile with this system, you can do so by following the link for Supplier Registration.

If you already have a supplier profile, please login to the Supplier Portal, then search for the negotiation using the reference number UNDP-PAK-01065, following the instructions in the user guide.

Introduction

The Merged Areas Governance Programme (MAGP) is a comprehensive governance initiative that focuses on technical assistance and implementation support to the Government of Khyber Pakhtunkhwa (GoKP) in three main areas: 1) accelerated development with an emphasis on the delivery of basic services; (2) border governance and connectivity; and (3) support to local governance systems. The overall objective of the Programme is to enhance the capacity of the GoKP to successfully integrate the Merged Areas and strengthen border governance and cross-border connectivity by extending laws, policies, and strategies; planning, designing, and delivering development initiatives; and implementing inclusive local government systems. An emphasis is placed on inclusive development, to ensure that marginalized population groups benefit from development in the MAs, as well as on disaster-risk reduction and improved risk management, to help prevent, mitigate and/or address the effects of climate change and other risks. 

An overview of the proposed work is tabulated as under:

S#

Name of The Scheme

District

Reference

Type of the schem

1

Street Pavement in Ferozkhel

Orakzai

1.1

Street Pavement

2

Water Tank and Pipeline Goeen Feroz Khel

Orakzai

1.2

Water supply and storage

3

Water Tank with washrooms and pipeline installation in Mela Bazar

Orakzai

1.3

Water supply and storage with Toilets

4

Pipeline (main) repairing and water tank rehab. Works in Baghnaak

Orakzai

1.4

Water Pipeline repairing and water tank rehab. Works

5

Construction 3000 Gallon SWT and Pipeline in Kharkay

Orakzai

1.5

Water supply and storage

6

Construction of 13000 GL SWT in Kot kaly

Orakzai

1.6

Water supply and storage

7

Pipeline and construction 3000 Gallon SWT in Ghotaak(Essa-Khel

Orakzai

1.7

Water supply and storage

8

Flood Protection Wall( for Existing Tube Well Infiltration gallery and building protection) in Chapri Meshthi

Orakzai

1.8

Protection ( for Existing Tube Well Infiltration gallery and building protection)

Project Timeline:

The duration of the timeline for District Packages Civil works will be 05 months. The time duration against each activity in the work plans of Lot 01 (1.1, 1.2, 1.3, 1.4, 1.5, 1.6, 1.7, 1.8) will be updated by the construction contractor as per the resources available. For work plans refer to annexure A.

Quality assurance and control:

The contractor will strictly comply with the technical specifications (Refer to Annexure B). All the construction activities will be executed as per standard practices mentioned in Annexure B.

A compliance sheet is to be filled in during the implementation of the project to ensure that standard practices are not being deviated. In case there is a deviation from the approved/standard works that must be reflected in the compliance sheet that is part of Annexure B.

HEALTH, SAFETY, SECURITY, AND ENVIRONMENT (HSSE) PROTOCOL GUIDANCE NOTE TO UNDP CIVIL PROJECT VENDORS

Health and Safety protocols must be adhered to on-site during the implementation phase.

For strict compliance, please refer to annexure C.         

Environmental considerations:

This aspect has been covered in the section 03: Environment Data and Mitigation Measures,

 of the assessment form. Please refer to annexures 1.2, 1.2, 1.3, 1.4, 1.5, 1.6, 1.7 and 1.8 for the details related to the environmental aspects of the respective projects.

Payment terms and milestones: Modality of Payment will be based on specified milestones.

For milestone details please refer to Annexure E.

Documents :

Negotiation Document(s) (Before Accessing other negotiations Document(s), please click on this link)