Scope of Work and Expected Outputs The scope of work of this TOR includes the remaining activities and outputs under Outcomes 3.1 & 3.2 - involving technology demonstrations assessment and replication planning as defined in Outputs 3.1.3 to 3.1.6 and Output 3.2.2 in the FASNETT Project Document (ProDoc). With the purpose of integrating all RE/EE projects at the national level, the assessment results and analysis of the above RE/EE technology pilot demos will be combined with assessments of the other existing and planned types of RE/EE applications in the country, e.g. solar home systems, roof-mounted solar generation, energy efficient home appliances, solar-powered devices, etc. The International Consultant will have the following scope of work and outputs and will be supported by a National Consultant. - Output 3.1.3: Successful demonstration of approved EE and RE technologies that promote and support Low Carbon (LC) development in the country and comparative evaluation report from monitoring with other existing RE/EE installations
This Output will involve the implementation of the following Activities: - Activity 3.1.3.1: Development and establishment of a computer-based M&E system for performance, maintenance and energy contributions of RE/EE project demonstrations and other existing RE/EE installations
- Activity 3.1.3.2: Evaluation of the design and operating performance and experiences in all demonstration and other existing RE/EE installations
- Output 3.1.4: Published energy performance and impact reports on implemented Low Carbon projects; including action plan for community-supported LC energy initiatives in island communities
This Output will Involve the documentation and dissemination of results and impacts of the RE/EE project demonstrations and the recommended action plan in promoting and replicating RE/EE projects for community-supported LC initiatives in island communities (Activity 3.1.4). The results of the monitoring and evaluation of all RE/EE projects gathered in Activity 3.1.3 will be published and shared via internet-based website (Output 1.6) for the project. This task will entail coordination with the EPC contractors of the demos and with TEC and DOE regarding the existing and planned RE/EE installations in the country to come up with a comprehensive report at the national level. - Output 3.1.5: Completed technical information packages and guidelines based on RE/EE project implementation experience for use in the capacity development program
This Output will involve the development and production of technical information packages and guidelines as inputs to the implementation of training workshops, strategic planning and execution of plans for national government authorities and local leaders in Component 2. This task will include inputs and coordination with the respective EPC contractors on the demos as well as TEC and DOE on the other types of RE/EE technologies applied in the country. - Output 3.1.6: Completed design and implementation plans for the replication of demonstrated successful LC energy projects
This Output will involve the implementation of the following Activities: - Activity 3.1.6.1: Development of standard design for replication of RE/EE applications in other areas of the country
- Activity 3.1.6.2: Development of technical inputs to the establishment and enforcement of basic design and operating guidance manuals for the RE/EE replication program and policy to be developed in Component 2.
This task will involve inputs and coordination with the respective EPC contractors on the demos as well as TEC and DOE regarding typical designs and implementation plans of the other feasible and practical types of RE/EE technologies to be applied in the country. To top the result of this assessment and technology designs, an Action Plan for the implementation of the replication of these selected RE/EE technologies will be submitted to be used as inputs to the formulation of the Tuvalu National Energy Plan (2023 – 2028) in Component 2. Close coordination with the IC and NC hired for Component 2 is required in order to synchronize plans at the national level. - Output 3.2.1: Completed and operational LC development technology application demonstrations in accordance to established quality standards in pilot tropical coastal communities enhancing market opportunities for RE/EE applications
This Output will involve the integration of the results of the FASNETT demos and of the required documentation by the EPC Contractors of the various experiences on procurement, delivery, installation, initial operation and debugging of the RE/EE facility as well as the associated technical services and training for the RE/EE demonstration projects. This task will also involve inputs and coordination with the respective EPC contractors on the demos as well as TEC and DOE regarding enhancing market opportunities of the feasible and practical types of RE/EE technologies to be applied in the country. - Output 3.2.2: Implemented LC projects in selected communities
This Output will involve the implementation of the following Activities: - Activity 3.2.2.1: Formulation and implementation of a technology development and application program for RE/EE in government, community–based and private business projects for selected island communities.
- Activity 3.2.2.2: Development and implementation of a technical assistance scheme for individual commercial and residential RE and EE project investment proposals from national government agencies, local community leaders and private entrepreneurs
A draft technology development and application plan for RE/EE in government, community–based and private business projects for selected island communities shall be developed and endorsed before the project ends in February 2023. However, a draft technology development and application plan shall submitted by end November 2022 in line with the Terminal Evaluation of the Project. The timeliness of outputs as well as the completeness and quality of the above-mentioned Outputs will be the overall responsibility of the International Consultant (IC) working in tandem with a National Consultant (NC) on-site as defined in this TOR. Deliverables The Activities under the above-mentioned Outputs, shall be implemented according to a proposed Activity Work Plan in order to optimize the time involved so that all outputs will be delivered within the duration of the Project as indicated in the approved time table: Deliverable #1: Inception Report - Overall approach and Activity Work Plan
Deliverable #2: Outputs 3.1.3 and 3.1.4 - Computer-based M&E system for performance, maintenance and energy contributions of RE/EE project demonstrations and other existing RE/EE installations
- Evaluation report on the design and operating performance and experiences in all demonstration and other existing RE/EE installations
Deliverable # 3: Outputs 3.1.5 and 3.1.6 - Developed and produced technical information packages and guidelines on FASNETT demo projects
- Developed standard design for replication of RE/EE applications in other areas of the country
- Developed technical inputs to the establishment and enforcement of basic design and operating guidance manuals for the RE/EE replication program and policy
Deliverable #4: Outputs 3.2.1 and 3.2.2 - Report on completed and operational FASNETT demos in accordance to established quality standards for enhancing market opportunities for RE/EE applications
- Report on a technology development and application program for RE/EE in government, community–based and private business projects for selected island communities
- Developed and facilitate approval of a technical assistance framework and scheme for individual commercial and residential RE and EE project investment proposals from national government agencies, local community leaders and private entrepreneurs.
Institutional Arrangement The principal responsibility of the IC is to implement the remaining Activities under Outcome 3 together with the support of a National Consultant, and in coordination the FASNETT Chief Technical Advisor (CTA). The IC and NC will work also with Project Implementation Support Officer in day-to-day matters. The IC will work closely with the NC and provide guidance to the NC in the needs for data and analysis, information, coordination with the PMU, DOE and TEC and in coming up with the committed deliverables through the performance of the above-listed duties. - The work of the IC and the NCs will be monitored, overseen and supervised by the FASNETT Project Manager as assisted by the CTA, and in close cooperation with the DOE/MTET, TEC and UNDP through the weekly project oversight and coordination meetings.
- The IC is expected to submit reports upon successful completion of activities in the approved Time Schedule/Activity Work Plan in Deliverable #1.
- The IC is expected to use his/her own computer in the conduct of this consultancy assignment.
Duration of the Work - The consultancy duration is for five (3) months and is expected to commence from 1 November 2022 to 31st January 2023;
- The Consultants shall be engaged to undertake the consultancy according to an approved Time Schedule/Activity Work Plan and is expected to complete the work by 31st January 2023.
Duty Station Because of the prevailing pandemic travel restriction and protocols, the IC will work as home-based assignment in providing the leadership, direction and overall responsibility in the accomplishment of the tasks and the expected deliverables, while the NCs, based in Funafuti, Tuvalu, will provide the data/info gathering, direct support, material inputs, on-site implementation and local facilitation. If possible and allowed by national protocols the IC may possibly be permitted to travel to Tuvalu within the duration of the Contract. Ideally, the IC should be able to travel to Tuvalu that would necessitate and possibly obtain government permit because of the nature of the tasks involving comprehensive workshops and hands-on training for the participants. PMU will endeavor to secure the necessary government permits and travel clearance when allowable. If the travel happens, the travel cost will be reimbursed by the project on actual economy basis. |